Client Overview
A leading utility company in Barbados approached TMR Fino Global to source and deliver a custom pad-mounted transformer to support the island's growing infrastructure.
Challenges
- The transformer had to withstand high humidity, salt air and heavy rainfall without compromising performance or lifespan.
- The client needed it shipped and installed within 8 weeks to meet project deadlines.
- Efficient packing and shipping arrangements were crucial to transport the transformer from India to Barbados without delays.
Solution by TMR Fino Global
We coordinated manufacturing with a trusted, vetted partner using state-of-the-art processes to ensure durability, efficiency and compliance with international standards like IEC 60076.
TMR Fino Global partnered with global shipping experts to ensure seamless, on-time delivery:
- Custom-engineered packing designed for the long sea route from India to Barbados.
- End-to-end logistics coordination across export, freight and customs clearance.
- Proactive scheduling to keep the shipment aligned with the client's 8-week deadline.
Results
- Completed the entire process — from design approval to manufacturing and shipping — in just 8 weeks, helping the client meet their project deadline.
- The transformer was delivered to Barbados on schedule, allowing the utility company to meet its infrastructure goals.
- It operates efficiently, handling the tropical environment without any issues since installation.
Client Testimonial
The client praised TMR Fino Global for their commitment to quality, customization and on-time delivery.